Day 1: Laying of chipboard for the storage area and make preparations for installation of steel RSJ beams. Day 2: Installation of Velux windows (weather permitting); assembly of steel beams; double up existing rafters. Day 3: Building up structural load-bearing wall to take the weight from the roof to steel beams; cut trusses to form the shape of … Continue reading Process